A rebar order is four numbers, not one: how many bars run each way, how long they are in total once laps are added, how much that length weighs, and how many stock sticks it divides into — because suppliers sell sticks, not feet. This rebar calculator takes the slab, footing or wall dimensions in feet or metres, a bar size (#3, #4 or #5, all verified against ASTM A615), a grid spacing in each direction (12, 18 or 24 in on centre, with metric equivalents), a stock length, a lap toggle and a waste allowance, and returns the bar count per direction, the total length in feet and metres, the weight in pounds, kilograms, US tons and tonnes, the stock sticks to buy, and a cost from your own price per pound or per stick — no prices are preset. Laps follow a stated 40x-diameter assumption (#4 = 20 in) and are added only where a bar run exceeds the stock length. For the concrete itself, use the concrete calculator.
Planning this project? Save to Pinterest to find this calculator again later.
How to use the Rebar Calculator
- Measure the slab, footing mat or wall grid length and width in feet or metres — the full dimensions, not the inside of the formwork. For a footing strip, length is the strip length and width is the strip width; for a wall, length is the wall length and width is the wall height.
- Pick the bar size from the plan: #3 for light patios, #4 as the usual residential slab and footing bar, #5 for heavier footings and walls. If the plan names a metric bar (10M, 13M, 16M), those are the same bars as #3, #4 and #5 in ASTM's soft-metric designation — pick the matching US size.
- Set the spacing in each direction: 18 in OC both ways is the standard 4 in slab grid, 12 in OC both ways suits driveways, shop floors and footings, and a rectangular grid (tighter one way) follows the plan. Do not pick 24 in OC for a slab — it exceeds ACI 318's 18 in slab cap — unless an engineer specifies it.
- Enter the stock length your supplier actually sells (commonly 20 ft / 6 m) and leave laps on. The tool splices only the bars that run longer than one stock length, at 40x bar diameter per splice (#4 = 20 in), and the stick count divides the ordered length by the same stock length.
- Set the waste allowance by the cutting: 10% for ordinary straight grids, 15-20% where many short bars, bends or a tight site waste more. The ordered length, the weight and the stick count all follow the waste figure — the net length does not.
- Read all five outputs, not just the bar count: bars per direction (what the grid looks like), total length in feet and metres (what you handle), weight in pounds, kilograms, tons and tonnes (what the truck carries), sticks to buy (what you order), and cost from your own price. A grid can look small in bars and still be heavy: 28 bars of #4 on a 20 x 20 ft slab is 411.49 lb ordered (373.28 lb net).
- Enter ONE price basis — per pound or per stick — and check that tying wire, chairs or dobies, cutting, bending, delivery and placing labour are either in your price or priced separately. If both price fields are filled, the per-pound price wins; the per-stick figure is then shown for reference only in the breakdown, not added to the total.
- Take the bar counts, the stick count and the weight to the supplier, and confirm the bar size, the stock length and the price basis on the order before paying. On site, hold the grid off the ground on chairs or dobies so it sits in the slab, never flat on the dirt — steel on the dirt ends up with no cover and rusts from below.
Rebar Calculator formula
Worked example
A 20 x 20 ft slab, #4 bars at 18 in OC both ways, laps on, 20 ft stock, 10% waste. Step one — bars per direction: bars running the length = floor(20 ft / 1.5 ft) + 1 = 13 + 1 = 14; bars running the width = floor(20 / 1.5) + 1 = 14; total 28 bars. Step two — net length: 14 x 20 ft + 14 x 20 ft = 560 ft (170.69 m); net weight 560 x 0.668 = 373.28 lb (169.66 kg). Step three — laps: each 20 ft bar fits one 20 ft stock length, so splices per bar = ceil(20 / 20) - 1 = 0 and lap length = 0 ft. Step four — ordered: 560 x 1.10 = 616 ft (187.76 m). Step five — weight: 616 x 0.668 = 411.49 lb (186.63 kg), 0.21 US tons (0.19 tonnes). Step six — sticks: ceil(616 / 20) = 31 sticks of 20 ft bar. Step seven — cost: at $0.50 per lb, 411.49 x $0.50 = $205.74; at $10 per stick instead, 31 x $10 = $310.00 (enter one price basis, not both — per-pound wins if both are entered).
Metric version: a 6 x 6 m slab, #4 (13 mm) bars at 45 cm OC both ways, laps on, 6 m stock, 10% waste. Bars per direction: floor(6 / 0.45) + 1 = 13 + 1 = 14; total 28 bars. Net: 28 x 6 m = 168 m (551.18 ft). Laps: 6 m bars fit 6 m stock, so 0 m of lap. Ordered: 168 x 1.10 = 184.80 m (606.30 ft). Weight: 184.80 x 0.994 = 183.69 kg (405.01 lb), 0.18 tonnes (0.20 US tons). Sticks: ceil(184.80 / 6) = 31 sticks of 6 m bar.
Lap version: the same grid stretched to 30 x 20 ft, #4, 18 in OC, 20 ft stock, laps on, 0% waste (waste 0 isolates the lap). Bars running the length = floor(20 / 1.5) + 1 = 14 bars of 30 ft; bars running the width = floor(30 / 1.5) + 1 = 21 bars of 20 ft; total 35 bars. Net: 14 x 30 + 21 x 20 = 840 ft. Laps: each 30 ft bar needs ceil(30 / 20) - 1 = 1 splice at 40 x 0.5 in = 20 in (1.667 ft), so 14 x 1 x 1.667 = 23.33 ft of lap; the 20 ft bars need none. Total: 840 + 23.33 = 863.33 ft; weight 863.33 x 0.668 = 576.71 lb (261.57 kg). With laps off, the same grid is 840 ft and 561.12 lb (254.50 kg) — the lap is worth 23.33 ft and 15.59 lb on this slab, and more on every longer run.
Bar sizes (ASTM A615 — verified, see Sources):
| Bar | Diameter | Area | Weight | Lap at 40x diameter |
|---|---|---|---|---|
| #3 (10M) | 3/8 in (9.5 mm) | 0.11 in² (71 mm²) | 0.376 lb/ft (0.560 kg/m) | 15 in (38 cm) |
| #4 (13M) | 1/2 in (12.7 mm) | 0.20 in² (129 mm²) | 0.668 lb/ft (0.994 kg/m) | 20 in (51 cm) |
| #5 (16M) | 5/8 in (15.9 mm) | 0.31 in² (199 mm²) | 1.043 lb/ft (1.552 kg/m) | 25 in (64 cm) |
Spacing guide (typical practice under ACI 318 caps — the plan governs):
| Element | Typical bar and spacing | Why |
|---|---|---|
| 4 in house slab / patio | #3 or #4 at 18 in OC both ways | Shrinkage/temperature mat; 18 in is the ACI slab cap (smaller of 5x thickness and 18 in for temperature steel) |
| 5-6 in driveway / shop floor | #4 at 12 in OC both ways | Heavier wheel loads; tighter grid controls cracking under load |
| Footing mat (wide footing) | #4 at 12 in OC both ways | Common footing-mat practice; cover 3 in minimum against earth |
| Narrow trench footing | Two continuous #4 or #5 bars on chairs | Not a grid — do not size it with this tool's two-way count; run it as two bars x strip length, plus laps |
| Wall grid | #4 at 12-18 in OC, engineer-specified | Verticals + horizontals; spacing follows the wall design, never a default |
| 24 in OC anywhere | Engineer-specified only | Exceeds ACI 318's 18 in slab cap — never a slab default |
Spacing changes the order fast (20 x 20 ft, #4, laps on, 20 ft stock, 10% waste): at 12 in OC, 21 + 21 = 42 bars, 840 ft net, 924 ft ordered, 617.23 lb (279.95 kg); at 18 in OC, 14 + 14 = 28 bars, 560 ft net, 616 ft ordered, 411.49 lb (186.63 kg); at 24 in OC, 11 + 11 = 22 bars, 440 ft net, 484 ft ordered, 323.31 lb (146.64 kg) — but 24 in exceeds the ACI slab cap, so the saving is not yours to take without an engineer.
Measurement tips
- Measure the full grid, not the inside of the formwork. The tool counts bars over the dimensions you enter; formwork, edge thickening and turndowns are inside those dimensions, not added to them. A slab measured short by 6 in at 18 in spacing can lose a whole bar per direction.
- Use the same spacing both ways unless the plan says otherwise. A square grid (18 in x 18 in) is the normal residential mat; a rectangular grid (12 in one way, 18 in the other) exists where the loads run one way, and guessing it wastes steel one way and leaves the other way light.
- Hold the grid off the ground. Bars flat on the dirt end up with no cover underneath and rust from below; chairs or concrete dobies hold the mat in the lower-to-middle third of the slab, where the steel can actually work. The grid count is the same — the position is what changes.
- Stagger the laps. Every splice at the same section makes one weak plane across the slab; offset neighbouring splices so no cross-section carries more than half its bars spliced at once (the ACI Class A condition — and the reason Class B, 1.3x, is the default everywhere else).
- Wire every lap at both ends. A lap that is not wired tight can open while the concrete is placed, and an opened lap is two bar ends touching — it carries nothing. Two wire ties per lap, one at each end, is the site habit.
- Keep the offcuts. Cutting 20 ft sticks to grid lengths leaves short pieces, and short pieces become dowels into the next pour, chair supports and tie wire anchors. The waste allowance pays for offcuts; throwing them away pays for them twice.
- Order by sticks, check by weight. The supplier picks sticks; the truck is loaded by weight. If the stick count and the weight disagree wildly (a 28-bar grid that weighs half what you expected), one of the inputs — usually the bar size — is wrong, and the weight check catches it before the truck leaves.
- Do not use 24 in spacing to save money on a slab. The ACI cap is 18 in for a reason: wider spacing leaves cracks wider apart and wider open. The 24 in option exists for engineer-specified footing mats and walls, not for a patio that happens to be expensive.
- For a footing, check the cover before the count. Concrete cast against earth needs 3 in of cover, so a footing bar is shorter than the footing and sits inside it — cut lengths come from the plan with cover deducted, even though this tool prices the order at full length (conservative, never short).
Common mistakes
- Counting bars in one direction only. A grid has bars both ways: a 20 x 20 ft slab at 18 in OC needs 14 bars running the length AND 14 running the width — 28 bars, not 14. Half the grid is the commonest rebar under-order.
- Dividing area by spacing instead of counting per direction. Area-based shortcuts (square feet divided by spacing) give a length, not a bar count, and they miss the +1 bar at the far end of each direction. Count per direction with floor(dimension / spacing) + 1, then add the two directions.
- Forgetting the +1 bar. floor(length / spacing) alone drops the end bar: a 20 ft slab at 18 in OC is floor(20 / 1.5) = 13 bays, which need 14 bars, not 13. Every direction needs its end bar.
- Forgetting laps on long runs. A 30 ft bar from 20 ft stock is not one bar — it is two bars plus a 20 in lap (#4). Ordering the net length with no lap leaves every long bar short by its splice, and the grid cannot be tied as drawn.
- Using 24 in spacing for a slab because it is cheaper. 24 in exceeds ACI 318's 18 in slab cap: the saving (22 bars instead of 28 on a 20 x 20 ft slab) buys wider cracks and a failed inspection. Tighter spacing is not conservatism — it is the cap.
- Pricing by net weight instead of ordered weight. The steel you pay for includes laps and waste: on the 20 x 20 ft example the net weight is 373.28 lb but the ordered weight is 411.49 lb. A quote that looks cheap on net weight is the same steel at a higher unit price.
- Entering both a per-pound and a per-stick price and adding them. The two price the same steel; this tool lets the per-pound price win and ignores the per-stick price when both are entered. Adding both charges the steel twice.
- Laying the grid flat on the dirt. Steel with no cover underneath corrodes, expands as it rusts and spalls the slab from below. Chairs or dobies cost little and are the difference between reinforcement and rust in a mat shape.
- Bunching every lap at the same section. Laps lined up across the slab create one plane where every bar is spliced at once — stagger them, and keep splices out of the highest-stress section where the plan says so.
- Sizing a narrow trench footing as a grid. Two continuous bars in a 12-18 in trench are not a two-way mat: running this tool on a trench footing double-counts steel that is not there. Price a trench footing as bars x strip length, plus laps, by hand.
Factors that affect accuracy
- Slab dimensions: every extra foot of length at 18 in spacing adds about two-thirds of a bar per direction in count terms — but bars come whole, so a dimension just over a spacing multiple costs a whole extra bar per direction. Measure twice: the count steps, it does not glide.
- Spacing in each direction: spacing is the fastest lever on the order. On a 20 x 20 ft slab at #4, tightening from 18 in to 12 in OC moves the order from 28 bars / 616 ft / 411.49 lb to 42 bars / 924 ft / 617.23 lb — a 50% increase for a 6 in tighter grid. Loosening to 24 in drops it to 22 bars / 484 ft / 323.31 lb, but breaks the ACI slab cap.
- Bar size: weight scales with the square of the diameter, so stepping from #4 to #5 on the same grid multiplies weight by 1.043 / 0.668 = 1.56 — a 56% weight increase for one size step, with no change in bar count. Size is a weight decision even when the count looks unchanged.
- Stock length: a 20 ft stock splices every bar longer than 20 ft; a 40 ft stock splices only bars longer than 40 ft. On a 30 ft grid, 20 ft stock adds 23.33 ft of lap (#4, 14 bars) while 40 ft stock adds none — but 40 ft sticks need a truck and a site that can handle them.
- Lap assumption: the tool assumes 40x diameter. A plan lap of 50x diameter adds 25% more lap length than the tool shows (25 in instead of 20 in for #4); a Class B 1.3x development-length lap can differ from both. The plan lap, where one exists, replaces this assumption.
- Waste percentage: waste multiplies the whole ordered length, so on the 20 x 20 ft example each 5% of waste is 28 ft and 18.70 lb of #4. Grids of short bars, bent bars and tight sites waste more than long straight grids — match the band to the cutting, not to optimism.
- Cover and cut length: cover shortens every real bar by about twice the cover (6 in per bar at 3 in earth cover) but the tool prices full length, so the order carries a small built-in surplus — roughly one extra stick per 40 bars at 3 in cover. Cut lengths still come from the plan.
- Element type: a slab mat, a footing mat and a wall grid share this arithmetic but not the spacing rules — slabs cap at 18 in, footings commonly sit at 12 in, walls follow the wall design. The same 20 x 20 ft numbers mean different things on a patio and on a retaining wall.
- Price basis: per-pound pricing follows the ordered weight (laps and waste included); per-stick pricing follows the stick count (rounded up, so a 616 ft order buys 31 sticks, not 30.8). On small orders the rounding in stick pricing can outweigh a small per-pound difference.
Sources & assumptions
- Bar sizes, diameters, areas and weights per ASTM A615 / A615M — via the ANSI webstore table of the standard: #3 [10] 0.375 in (9.5 mm), 0.11 in2 (71 mm2), 0.376 lb/ft (0.560 kg/m); #4 [13] 0.500 in (12.7 mm), 0.20 in2 (129 mm2), 0.668 lb/ft (0.994 kg/m); #5 [16] 0.625 in (15.9 mm), 0.31 in2 (199 mm2), 1.043 lb/ft (1.552 kg/m). US bar numbers are eighths of an inch up to #8, and weight depends only on nominal diameter, not grade. Some secondary tables round #5 area to 200 mm2; this page publishes the ASTM table's 199 mm2. The three brief figures (0.376 / 0.668 / 1.043 lb/ft) were re-verified against this table, not trusted blindly.
- Spacing caps and typical practice (ACI 318 guidance, basis labelled): slab spacing is capped at the smaller of a thickness multiple and 18 in — 3x thickness for flexural steel and 5x thickness for shrinkage/temperature steel per EngineerFix's spacing guide (3x / 18 in for standard slabs) and the older ACI 318 §7.12 formulation quoted on Eng-Tips (5x thickness or 18 in for shrinkage/temperature steel). Common residential practice: #3 or #4 at 18 in OC for a 4 in slab, #4 at 12 in OC for 5-6 in driveways and shop floors, #4 at 12 in OC for footing mats, two continuous bars in narrow trench footings — per the crushed-concrete rebar guide's slab/footing summary and the footing-spacing guide's 12 in OC footing practice. 24 in OC exceeds the 18 in slab cap and is offered for engineer-specified layouts only.
- Lap (stated planning assumption, 40x diameter): tension laps run roughly 40-50 bar diameters in practice, and 40x is this tool's assumption — #3 = 15 in, #4 = 20 in, #5 = 25 in, all above ACI 318's 12 in absolute minimum for lap splices (Class A = 1.0x development length, Class B = 1.3x the default, per the lap-length reference). The true required lap depends on concrete strength, bar grade, cover and spacing, so a plan lap governs where one exists. Stock length default 20 ft (6 m) is the commonly stocked stick length, with 40 ft (12 m) also stocked; the user enters their supplier's real length.
- Bar count (this tool's stated method): bars per direction = floor(dimension / spacing) + 1 — the standard estimating convention, cross-checked against the published 20 ft slab example (20 ft at 12 in OC = floor(20/1) + 1 = 21 bars per direction, 42 bars, 840 ft net, 561.12 lb of #4). Where a dimension is not an exact multiple of the spacing, a plan requiring an edge bar at both ends needs ceil + 1 instead (at most one extra bar per direction) — the page states this. Cover simplification: concrete cast against earth needs 3 in minimum cover (EngineerFix, same spacing guide), so real bars run about twice the cover shorter than the tool's full-length figures; the order is therefore slightly conservative, never short.
- Canonical example (this tool): 20 x 20 ft, #4, 18 in OC both ways, laps on, 20 ft stock, 10% waste — bars 14 + 14 = 28; net 560 ft (170.69 m), 373.28 lb (169.66 kg) net; splices 0, laps 0 ft; ordered 616 ft (187.76 m); weight 616 x 0.668 = 411.49 lb (186.63 kg), 0.21 US tons (0.19 tonnes); sticks ceil(616 / 20) = 31; cost at $0.50/lb = $205.74, or at $10/stick = $310.00. Metric twin: 6 x 6 m, #4 (13 mm), 45 cm OC, 6 m stock, 10% waste — 28 bars, net 168 m (551.18 ft), ordered 184.80 m (606.30 ft), 183.69 kg (405.01 lb), 31 sticks. Lap example: 30 x 20 ft, #4, 18 in OC, 20 ft stock, laps on, 0% waste — 35 bars, net 840 ft, laps 23.33 ft (fourteen 30 ft bars x one 20 in splice), total 863.33 ft, 576.71 lb (261.57 kg); laps off 840 ft, 561.12 lb (254.50 kg).
- Cost, when shown, uses only the price per pound or per stock stick you enter — no prices are preset — and only the steel itself. The two price bases are alternatives for the same steel: if both are entered, the per-pound price wins and the per-stick price is ignored, never added.
Figures checked on 28 November 2026 as part of the site-wide test run (3239 automated checks, all passing). See how we calculate and test.
Safety note
What this calculator doesn't do
- This tool sizes a material order for one rectangular slab, footing strip grid or wall grid, not a structural design. It does not check whether your bar size and spacing are legal for the loads your slab, footing or wall actually carries — load-bearing footings, walls under lateral load, suspended slabs and anything on an engineered plan need the plan's bar schedule or an engineer. The spacing guidance on this page is typical practice under ACI 318 caps, not approval for your job.
- Bar count uses floor(dimension / spacing) + 1 per direction — the standard estimating convention. Where a dimension is not an exact multiple of the spacing, the last bay stretches wider than the spacing. A plan that requires a bar at both edges regardless of the spacing fit needs ceil(dimension / spacing) + 1 instead — at most one extra bar per direction. If your plan shows an edge bar at both ends on a non-multiple dimension, add one bar per direction by hand.
- Bar lengths are the FULL slab dimensions. Real bars are pulled in by concrete cover on every side (3 in minimum where concrete is cast against and permanently exposed to earth, such as a footing), so a real bar runs about twice the cover shorter than the tool's length. The tool's lengths therefore read slightly long — conservative for ordering, never short — but cut lengths must come from the plan, not from this page.
- The lap length is a planning assumption, not a code calculation: 40x bar diameter (#3 = 15 in, #4 = 20 in, #5 = 25 in). ACI 318 lap splices are Class A (1.0x development length) or Class B (1.3x, the default on most sites) with a 12 in absolute minimum, and the true required lap depends on concrete strength, bar grade, cover and bar spacing. If your plan specifies a lap, use the plan's lap: turn laps off here and add the plan lap by hand, or check that the plan lap and this tool's 40x lap agree before ordering.
- Laps are added only where a bar run exceeds the stock length (20 ft / 6 m default). If your supplier stocks a different length, enter it — the splice count follows it. Stagger laps (never bunch every splice at the same section) and wire every lap at both ends; a lap that is not wired can open during the pour.
- 24 in spacing exceeds ACI 318's 18 in slab maximum. The tool offers it only for engineer-specified layouts (some footing mats and walls); do not use 24 in OC for a slab on this page's say-so. If in doubt, use 18 in or tighter and check the plan.
- Weight is computed on the ORDERED length (net + laps, plus waste), i.e. the weight you buy — it is higher than the net weight of steel in the finished slab. If your supplier quotes by net weight, the difference is the laps plus the waste percentage.
- The stick count divides the ordered length by the stock length and rounds up — it is a purchase quantity, not a cut plan. Cutting 20 ft sticks to your grid lengths leaves offcuts; the waste allowance covers ordinary offcuts, but a grid of many short bars wastes more than a grid of long ones. Keep offcuts: short pieces become dowels, chairs and ties.
- Cost uses the prices you enter — no prices are preset — and only the steel itself. Tying wire, bar chairs or concrete dobies to hold the grid off the ground, cutting, bending, delivery and placing labour are not in this total unless your entered prices already include them. Enter a price per pound OR a price per stick: if you enter both, the per-pound price wins and the per-stick price is ignored, because the two price the same steel twice.
- This page does not cover wire mesh (WWR), fibre reinforcement, epoxy-coated or stainless bar, post-tensioning, or bent bars (hooks, stirrups, dowels). A slab reinforced with mesh instead of loose bars is sized by mesh sheet area, not by this grid — and a footing that needs vertical dowels or a wall that needs horizontal bond beams needs those bars added separately.
- For the concrete the bars go into, use the concrete calculator; for a block wall the bars reinforce, the concrete block calculator; for the holes a fence or deck footing grid sits in, the post hole calculator; for the timber frame that sits on the slab, the framing calculator.
Rebar Calculator — frequently asked questions
How many rebars do I need for a 20x20 slab?
At the standard grid — #4 bars at 18 in OC both ways, 20 ft stock, laps on, 10% waste — a 20 x 20 ft slab needs 14 bars running the length + 14 running the width = 28 bars, 616 ft (187.76 m) ordered, 411.49 lb (186.63 kg), 31 sticks of 20 ft bar. At 12 in OC the same slab needs 42 bars, 924 ft and 617.23 lb; at 24 in OC it needs 22 bars, 484 ft and 323.31 lb — but 24 in exceeds the ACI 18 in slab cap, so do not use it for a slab without an engineer.
How much rebar do I need for a 10x10 slab?
At the default grid (#4, 18 in OC both ways, laps on, 20 ft stock, 10% waste), a 10 x 10 ft slab (100 sq ft) needs 7 + 7 = 14 bars, 154 ft (46.94 m) ordered, 102.87 lb (46.66 kg), 8 sticks of 20 ft bar. Net (before waste) it is 140 ft and 93.52 lb — the waste adds 14 ft and 9.35 lb. Scale by area for other square slabs: a 20 x 20 ft slab is four times the area and needs 28 bars, 616 ft and 411.49 lb at the same grid.
How many bars do I need for a footing?
For a footing MAT (a wide footing reinforced both ways), count it like a slab: bars per direction = floor(dimension / spacing) + 1, commonly #4 at 12 in OC. A 20 x 4 ft footing mat at 12 in OC needs floor(4 / 1) + 1 = 5 bars running the length and floor(20 / 1) + 1 = 21 bars running the width — 26 bars, 5 x 20 ft + 21 x 4 ft = 184 ft net, 202.40 ft and 135.20 lb of #4 at 10% waste (laps 0, since no bar exceeds 20 ft stock), 11 sticks. A NARROW trench footing is different: two continuous bars x strip length, plus laps — do not size it as a grid.
How much rebar do I need in kg for a 6x6 m slab?
At #4 (13 mm) bars at 45 cm OC both ways, laps on, 6 m stock, 10% waste, a 6 x 6 m slab needs 14 + 14 = 28 bars, 184.80 m ordered (606.30 ft) and 183.69 kg (405.01 lb), 31 sticks of 6 m bar. Net (before waste) it is 168 m and 167.00 kg — the waste adds 16.80 m and 16.69 kg. Enter metres for length and width above and the tool returns kilograms, tonnes and metres alongside the imperial figures.
How many kilograms of rebar do I need for a 3x3 m slab?
At the default grid (#4 / 13 mm, 45 cm OC both ways, laps on, 6 m stock, 10% waste), a 3 x 3 m slab needs 7 + 7 = 14 bars (floor(3 / 0.45) + 1 = 7 per direction), 46.20 m ordered (151.57 ft) and 45.92 kg (101.25 lb), 8 sticks of 6 m bar. Net it is 42 m and 41.75 kg. A 3 x 3 m slab is one quarter of a 6 x 6 m slab by area, and the steel scales the same way: 45.92 kg against 183.69 kg.
How much does rebar weigh per foot?
Per ASTM A615: #3 weighs 0.376 lb/ft (0.560 kg/m), #4 weighs 0.668 lb/ft (0.994 kg/m), and #5 weighs 1.043 lb/ft (1.552 kg/m). Weight depends only on the diameter, not the grade. So 100 ft of #4 weighs 66.80 lb (30.30 kg), 100 ft of #3 weighs 37.60 lb (17.07 kg), and 100 ft of #5 weighs 104.30 lb (47.30 kg) — and one 20 ft stick of #4 weighs 13.36 lb (6.06 kg).
How many 20 ft sticks of rebar do I need?
Divide the ordered length by 20 ft and round up: sticks = ceil(ordered length / 20). The 20 x 20 ft example orders 616 ft, so ceil(616 / 20) = 31 sticks; the 10 x 10 ft slab orders 154 ft, so ceil(154 / 20) = 8 sticks; the 30 x 20 ft lap example orders 863.33 ft with laps on, so ceil(863.33 / 20) = 44 sticks. If your supplier stocks 40 ft (12 m) sticks instead, enter 40 ft as the stock length — the 20 x 20 ft order then needs ceil(616 / 40) = 16 sticks, and no laps at all on bars up to 40 ft.
How much lap length do I need for rebar?
This tool assumes 40x bar diameter per splice: #3 = 15 in (38 cm), #4 = 20 in (51 cm), #5 = 25 in (64 cm) — all above ACI 318's 12 in absolute minimum. Laps apply only where a bar run exceeds the stock length: on a 30 x 20 ft slab with 20 ft stock, the fourteen 30 ft #4 bars each need one 20 in lap, adding 23.33 ft in total, while the twenty-one 20 ft bars need none. ACI 318's true requirement is Class A (1.0x development length) or Class B (1.3x, the default) and depends on concrete strength, grade, cover and spacing — if your plan specifies a lap, the plan lap governs.
How many rebars do I need for a wall?
Count a wall grid like a slab with length = wall length and width = wall height: bars per direction = floor(dimension / spacing) + 1. A 20 ft long x 8 ft high wall at #4, 12 in OC both ways needs floor(20 / 1) + 1 = 21 verticals running the height plus floor(8 / 1) + 1 = 9 horizontals running the length — 30 bars, 21 x 8 ft + 9 x 20 ft = 348 ft net, 382.80 ft and 255.71 lb at 10% waste (laps 0 at 20 ft stock), 20 sticks. Wall spacing is engineer-specified: do not default a wall to 18 in OC the way a patio slab defaults.
What spacing should rebar be for a concrete slab?
Typical practice under ACI 318 caps: #3 or #4 at 18 in OC both ways for a 4 in house slab or patio; #4 at 12 in OC for 5-6 in driveways and shop floors. ACI 318 caps slab spacing at the smaller of a multiple of slab thickness and 18 in (3x thickness for flexural steel, 5x for shrinkage/temperature steel) — so 24 in OC exceeds the cap for slabs and is engineer-specified only. Footings commonly sit at 12 in OC (or two continuous bars in a narrow trench); walls follow the wall design. When in doubt, use the tighter spacing and check the plan.
How much does rebar cost for a slab?
This calculator presets no prices — enter your supplier's price per pound or per stick. As an illustration with entered prices, the 20 x 20 ft example (411.49 lb ordered, 31 sticks) costs 411.49 x $0.50 = $205.74 at $0.50 per lb, or 31 x $10 = $310.00 at $10 per stick — enter one basis, not both (per-pound wins if both are entered). Tying wire, chairs or dobies, cutting, bending, delivery and placing labour are extra unless your price includes them. Get a supplier quote for the real figure.
How much rebar do I need for a driveway?
Driveways are 5-6 in slabs, so the usual grid is #4 at 12 in OC both ways. A 20 x 12 ft driveway bay at that grid needs floor(12 / 1) + 1 = 13 bars running the length and floor(20 / 1) + 1 = 21 bars running the width — 34 bars, 13 x 20 ft + 21 x 12 ft = 512 ft net, 563.20 ft and 376.22 lb at 10% waste (laps 0 at 20 ft stock: the longest bar is 20 ft), 29 sticks. Control joints, not rebar, handle most driveway cracking — the grid is there for load, and the joints still need cutting.
Next step
Take the bar counts, the stick count and the weight to the supplier — and confirm the bar size, the stock length and the price basis on the order before paying, since a wrong bar size changes the weight by 56% per size step (#4 to #5) with no change in bar count. Then price the concrete the bars go into with the concrete calculator and check the lap positions and cover against your plan before the pour.
Save this estimate: use the Copy link button in the results box above to share these exact inputs, or Print results for a paper copy to take to the store.