This paver calculator tells you exactly how many pavers to buy, how much crushed-stone base to have delivered, and how much bedding sand you will need for a patio, walkway, or driveway. Punch in the patio length and width, your paver size, and a cutting-waste percentage, and it returns a paver count rounded up to the whole paver, plus base and sand volumes in cubic yards and cubic feet. The waste allowance defaults to 10 percent, but the right figure depends on your laying pattern — 2 percent for stacked bond, 5 percent for running bond, up to 15 percent for herringbone at 45 degrees — and the waste-by-pattern table further down this page splits it out in full. The base depth defaults to 4 inches of compacted crushed stone and the sand to 1 inch of coarse bedding sand, both adjustable for your soil and load. Getting the order right matters because pavers are sold by the pallet and bulk material by the yard. Come up short and you are paying a second delivery fee, usually $75 to $150, and gambling that the next batch matches the color of the first. Over-order badly and you have spent real money on pavers and stone that sit behind your garage forever. Still deciding between pavers and a poured slab? Our concrete vs pavers guide compares cost, durability and looks.
Planning this project? Save to Pinterest to find this calculator again later.
How to use the Paver Calculator
- Measure the patio length and width in feet. For an irregular shape, measure the largest rectangle that covers it and accept that the waste allowance will absorb the offcuts.
- Enter the length and width of one paver in inches or centimetres. A standard Holland paver is 4 by 8 inches; Belgard and Unilock catalog pavers run larger, so measure an actual paver, not the catalog listing.
- Set the waste allowance from your laying pattern: 2 percent for stacked bond, 5 percent for running bond, 5 to 8 percent for basket weave, 10 percent for herringbone at 90 degrees, and 15 percent for herringbone at 45 degrees, which eats angled cuts all along the border. The full split is in the waste-by-pattern table below the worked example.
- Set the base depth. Four inches of compacted crushed stone is the standard for patios and walkways; driveways need six to eight inches.
- Set the bedding sand depth. One inch of coarse concrete sand is the standard screeded layer.
- Press Calculate. You get the paver count with waste already added, plus base and sand volumes in cubic feet and cubic yards, which is how bulk yards sell it.
- Read the breakdown and order by pallet for pavers and by the cubic yard for base and sand. Yards round up, so take the decimal seriously.
Paver Calculator formula
Worked example
Say you are building a 16 by 12 foot patio with 6 by 9 inch pavers and 10 percent waste. First the pavers. The patio is 192 square feet. One paver covers 9/12 times 6/12 feet, which is 0.375 square feet. 192 divided by 0.375 gives 512 pavers exactly, and 10 percent waste brings that to 563.2, rounded up to 564 pavers. That is roughly five pallets at a typical 108-paver pallet. Now the base. Four inches is one-third of a foot, so 192 square feet times one-third foot equals 64 cubic feet. Divide by 27 to get cubic yards: 64 / 27 = 2.37, so 2.37 cubic yards of crushed stone. Crushed stone weighs about 1.4 tons per yard, so 2.37 yards is about 3.3 tons; order 3.5 tons and you have margin. The sand layer is one inch, which is one-twelfth of a foot: 192 times 1/12 equals 16 cubic feet, and 16 / 27 = 0.59, so 0.59 cubic yards of coarse bedding sand. At a typical yard price of $40 to $60 per yard for base stone and $45 to $70 per yard for mason sand, the bulk material for this patio runs roughly $130 to $215 before the pavers themselves. One delivery, one batch of pavers, no second trip.
Paver waste by laying pattern
The waste percentage is not one number. The pattern sets it, because the pattern decides how many pavers get cut at the border and how much of each cut piece can be used again. Straight patterns waste little: their edge cuts are straight, and the offcuts usually fit somewhere else. Diagonal patterns waste the most, because every border cut is angled and the offcut rarely fits anywhere. Find your pattern in the table, then type that figure into the waste field above.
| Laying pattern | Waste to add | Why |
|---|---|---|
| Stacked bond | 2% | Rows and columns line up, so border cuts are straight and most offcuts fit back in. |
| Running bond | 5% | Half-offset rows still cut straight; only the staggered ends add a little waste. |
| Basket weave | 5–8% | Pairs turn at right angles, so more border pieces are cut to size; big patios sit at the low end. |
| Herringbone at 90° | 10% | The zigzag edge leaves a triangular gap at every border paver, filled with angled cuts. |
| Herringbone at 45° | 15% | The whole field runs diagonally, so every border paver is cut at 45 degrees and the offcuts are scrap. |
Two cautions. These figures are for a rectangle with straight edges — curves and circles add cuts on top of any pattern, so treat the table as a floor, not a ceiling, on a free-form design. And if you land between two figures, take the higher one: a leftover half-pallet becomes your spare-parts shelf, while a shortage is a second delivery fee and a colour-match gamble.
Measurement tips
- Order all your pavers from the same production batch. Pavers from different batches can be visibly different shades, and once they are down you cannot unsee it.
- Compact the base in 2-inch lifts with a plate compactor, not in one thick dump. A rented compactor costs about $60 to $80 a day at Home Depot and is the difference between a patio that stays flat and one that sinks.
- Put down landscape fabric under the base on clay soil. It is cheap insurance that stops the stone from sinking into the mud over the years.
- Slope the patio a quarter inch per foot away from the house. That is 2 inches over 8 feet, and it keeps rain from pooling at your foundation.
- Screed the sand dead level with a straight 2x4 riding on two screed rails. Every lump in the sand telegraphs straight through to the finished pavers.
- Install edge restraints before you lay a single paver. Plastic edge restraint with 10-inch spikes is about $1 per linear foot and stops the whole patio from creeping outward.
- Sweep polymeric sand into the joints and mist it, per the bag instructions. It locks the pavers together and stops weeds from moving in between.
- Buy a cheap wet saw or rent one for about $70 a day. A 4-inch angle grinder with a diamond blade works for small cuts, but the dust is brutal, so cut wet.
Common mistakes
- Laying pavers directly on dirt or bare sand with no crushed-stone base. It looks fine for a month. Then the first rainy season settles everything unevenly and you are re-laying the whole patio.
- Using fine play sand as bedding sand. Play sand shifts under load; coarse concrete sand is angular and locks together. Your patio can tell the difference even if your eyes cannot.
- Guessing the patio is a neat rectangle when it has curves. Curves multiply edge cuts, and the 10 percent default waste will not cover a free-form design. Bump it to 15.
- Ordering base stone in bags from the home center. You need yards, not bags. Bulk delivery at $40 to $60 a yard is a fraction of the bagged price, and bagged stone gets expensive around yard number two — see the paver patio cost guide for the full installed breakdown.
- Forgetting that pallets of pavers weigh close to 3,000 pounds. Tell the delivery driver where to drop it, because you are not moving it twice.
- Skipping the edge restraint to save twenty bucks. Within a season the outer row of pavers starts drifting and the whole border loosens. It is the cheapest material on the job and the most skipped.
Factors that affect accuracy
- Soil type. Sandy soil drains and compacts easily; clay holds water and heaves. On clay, add an inch or two to the base depth or put geotextile fabric under the stone.
- Load. Foot traffic and furniture do fine on 4 inches of base. A driveway with cars needs 6 to 8 inches of compacted base, which roughly doubles your stone volume. For a poured concrete driveway instead, the concrete calculator sizes the slab.
- Pattern. Waste follows the layout: stacked bond wastes about 2 percent, running bond 5 percent, basket weave 5 to 8 percent, and herringbone 10 percent at 90 degrees and 15 percent at 45 degrees, because the diagonal border cuts turn more of each paver into scrap.
- Edge shape. Straight edges produce neat half-paver cuts you can reuse. Curves and circles produce wedge-shaped offcuts you cannot, so curved designs need the higher waste allowance.
- Paver size. Large-format pavers lay fast but cut awkwardly around curves, producing more waste per cut. Small pavers cut cleaner on curves but take longer to lay.
- Compaction. Base stone compacts to about 80 percent of its loose volume. Order by the compacted depth the calculator gives you, since bulk yards price loose yards and you will lose some to compaction.
Sources & assumptions
- Pavers = patio area ÷ one paver's area × (1 + waste %), rounded up.
- Base and bedding sand volumes = patio area × the depths you enter.
- Depths are your inputs — see the FAQ for typical base depth.
- Base and bedding practice follows Interlocking Concrete Pavement Institute (ICPI) guidance.
Figures checked on 28 November 2026 as part of the site-wide test run (3239 automated checks, all passing). See how we calculate and test.
What this calculator doesn't do
- Base gravel, bedding sand and polymeric joint sand aren't in the paver count.
- Curves and circles need far more cuts than a rectangle — raise the waste percentage.
- It doesn't advise on drainage or grading; water needs somewhere to go.
Paver Calculator — frequently asked questions
How many pavers do I need for a 16x12 patio?
With 6 by 9 inch pavers and 10 percent waste: 564 pavers. That is about five pallets at a typical 108 pavers per pallet. Add 2.37 cubic yards of crushed-stone base and 0.59 cubic yards of bedding sand.
How deep should the paver base be?
Four inches of compacted crushed stone for patios and walkways; six to eight inches for driveways. Compact it in 2-inch lifts with a plate compactor, because a thick layer dumped all at once never compacts evenly.
Can I lay pavers on sand without a stone base?
You can, and you will regret it. Sand alone shifts and settles, and within a season or two the patio goes lumpy. The compacted crushed-stone base is what keeps a paver patio flat for a decade.
What is the difference between bedding sand and polymeric sand?
Bedding sand is the 1-inch layer of coarse concrete sand screeded under the pavers for levelling. Polymeric sand is swept into the joints between the pavers after they are laid, then misted with water so it hardens and locks the pavers together.
Should I use 10 or 15 percent waste for pavers?
Neither, until you pick a pattern — waste follows the layout. Use 2 percent for stacked bond, 5 percent for running bond, 5 to 8 percent for basket weave, 10 percent for herringbone at 90 degrees and 15 percent for herringbone at 45 degrees. The 10 percent calculator default is just a middle starting point; the waste-by-pattern table on this page has the full split. Curved edges push any pattern higher.
How much does a pallet of pavers cover?
A standard pallet of 4 by 8 inch Holland pavers covers about 108 to 120 square feet, depending on the manufacturer. Larger pavers cover more square footage per pallet. Check the coverage on the product tag rather than guessing.
What kind of gravel goes under pavers?
Crushed stone, often sold as 3/4-inch minus, crusher run, or 21AA, depending on your region. It has angular faces that interlock when compacted. Rounded pea gravel does not interlock and should never be your base layer.
How many pavers do I need for a 12x12 patio?
A 12 × 12 patio is 144 square feet. With standard 4 × 8-inch pavers there are 4.5 pavers per square foot, so the exact count is 144 × 4.5 = 648 pavers; add 10% waste for edge cuts and breakage and you get 648 × 1.10 = 712.8, so buy 713. Other common sizes: 6 × 6-inch pavers cover 4 per square foot (576 exact, 634 with waste), and 6 × 9-inch pavers cover about 2.67 per square foot (384 exact, 423 with waste). For the joints, budget polymeric sand at about 1 bag per 75–100 square feet for narrow joints — 2 bags for a 12 × 12 patio — or 1 bag per 25–50 square feet for wide joints, which is 3–6 bags. Enter your own patio size and paver size in the calculator above for an exact count.
How many pavers are there per square foot?
It depends on paver size, before waste: 4 × 8-inch pavers cover 4.5 per square foot, 6 × 6-inch cover 4, 6 × 9-inch cover about 2.67, and 12 × 12-inch cover 1. Multiply by your area, then add your waste percentage — 2% for stacked bond, 5% for running bond, up to 15% for herringbone at 45 degrees.
How much sand do I need under pavers?
Bedding sand goes 1 inch deep under the pavers: cubic yards = square feet ÷ 324. A 200-square-foot patio needs 200 ÷ 324 = 0.62 cubic yards of bedding sand. The crushed-stone base underneath is separate — 4 inches for patios, 6–8 for driveways — and the calculator above shows both numbers for your patio.
Next step
Take the paver and base-gravel totals to the landscape supplier, and confirm base depth for your soil — soft or clay soil needs a deeper base. The concrete vs pavers guide helps if you're still choosing.
Save this estimate: use the Copy link button in the results box above to share these exact inputs, or Print results for a paper copy to take to the store.