Concrete Steps Calculator

Concrete steps are not a slab and not a column — two volumes stack on top of each other. Underneath runs an inclined waist slab, a rectangle tilted up the slope of the flight; on top of it sit the triangular step wedges that form each tread and riser. Price only one of them and you run short mid-pour; price both as solid boxes and you order nearly twice what the stair actually takes. This concrete steps calculator does both volumes properly: enter the total rise, your target riser and tread, the stair width and the slab thickness, and it returns the step count, the actual riser height, the total run, the slab and wedge volumes separately, the total in cubic yards and cubic metres, bag counts, weight and cost — plus a check of your risers and treads against the residential code limits. For the timber layout of the same flight, use the stair calculator; for flat work, the concrete calculator; and for the steel inside the pour, the rebar calculator.

Quick answer: A 35 in rise with 7 in risers and 11 in treads on a 4 ft wide stair needs 5 risers, 4 treads and a 44 in run — and 0.51 cubic yards of concrete (0.56 with 10% waste), or 26 x 80-lb bags. The inclined waist slab is 9.37 ft³ and the four step wedges add 4.28 ft³. Risers of 7 in and treads of 11 in pass the IRC limits (7.75 in maximum riser, 10 in minimum tread). Enter your own rise and width to get your number.
Vertical height from the lower finished surface to the top of the porch or upper floor — measure between finished surfaces, including any flooring.
Height you want per step. 7 in (18 cm) climbs comfortably; the residential code caps risers at 7.75 in (19.7 cm). The tool rounds to whole steps and spreads the rise evenly.
Horizontal depth of each step, nosing to nosing. 10–11 in (25–28 cm) is typical; the code minimum is 10 in with a nosing.
Width of the steps, side to side. The code minimum for a residential stair is 36 in (91 cm); 4 ft is a common porch width.
Structural thickness of the inclined slab, measured perpendicular to the slope. 6 in is typical for a low residential flight (5–7 in); your engineer's figure governs for anything structural.
Length of a bottom landing pad, if you are pouring one with the steps. Leave blank for no landing — the steps alone are priced.
Thickness of the landing pad. 4 in is standard for foot traffic on compacted gravel; it only matters if you entered a landing length.
Extra for spillage, over-excavation and uneven subgrade. 10% is standard for steps — formwork leaks and the subgrade under a stair is rarely flat.
Your plant's delivered price per cubic yard, in dollars — leave blank to skip the ready-mix cost. Ask about the short-load fee under about 3 yards.
Your store price per 80-lb bag, in dollars — leave blank to skip the bagged cost. Bags make sense under about a cubic yard; above that, ready-mix usually wins.

Planning this project? Save to Pinterest to find this calculator again later.

How to use the Concrete Steps Calculator

  1. Measure the total rise first — the vertical distance from the finished lower surface (patio, walkway or ground) to the finished upper surface (top of the porch or floor). Measure between finished surfaces, including flooring thickness; every number below hangs on this one.
  2. Pick a target riser height. Seven inches (about 18 cm) climbs comfortably for most people. The tool rounds your target to a whole number of risers and then divides the rise evenly, so every riser is identical — which is what keeps stairs safe and what the code requires (no more than 3/8 in variation in a flight).
  3. Pick a tread depth. Eleven inches (about 28 cm) fits a full footstep; 10 in is the code minimum when the tread has a nosing. Check the 2 x riser + tread comfort figure in the results: near 24–25 in (61–64 cm) feels natural.
  4. Enter the stair width and the waist slab thickness. Width is side to side — 4 ft is a common porch width and 36 in is the code minimum. Slab thickness is measured perpendicular to the slope, not vertically: 6 in is typical for a low residential flight.
  5. Add a landing only if you are pouring one. A bottom landing pad is a plain rectangle — length x stair width x thickness — and the tool adds it as its own line. Leave it blank if the steps land straight on a walkway.
  6. Set the waste allowance. Steps deserve 10% rather than the 5% a flat slab gets: formwork leaks at the joints, the subgrade under a stair is rarely flat, and a short pour has nowhere to hide a shortage.
  7. Read the two volumes separately. The waist slab is the big number on a long flight; the wedges are the big number on a short, wide one. If either looks wrong, check the slab length (the diagonal) and the wedge count (one per tread, not per riser) against the breakdown.
  8. Read the code check before you form anything. It flags a riser over 7.75 in, a tread under 10 in, a stair narrower than 36 in, or a flight taller than 151 in — and it tells you the fix, which is usually one more riser.
  9. Decide bags versus ready-mix from the bag count. Under about 45 bags (one cubic yard) bags are practical; past about 1.5–2 cubic yards, ready-mix is faster and usually cheaper per yard. Enter both prices to see the two totals side by side.
  10. Order the concrete last, after the forms are built and braced. Re-measure the formed width and the slab thickness in the forms before you call — a form that bowed out by half an inch over a 4 ft width adds real volume, and the waste allowance is there for exactly that.

Concrete Steps Calculator formula

Risers = total rise / target riser height, rounded to the nearest whole number — adding one more riser if that would push any riser over the 7.75 in (19.7 cm) code maximum. Actual riser height = total rise / number of risers, so every riser is identical. Treads = risers - 1, because the porch or upper floor serves as the final tread. Total run = treads x tread depth. Waist slab length = √(total run² + total rise²), the Pythagorean theorem on the whole flight. Waist slab volume = slab length x stair width x slab thickness. Step wedges = ½ x treads x tread depth x actual riser height x stair width — each wedge is half a box in cross-section. Landing volume (if any) = landing length x stair width x landing thickness. Total volume = slab + wedges + landing, then waste is added: order volume = total x (1 + waste%). Bags = order volume / yield per bag, rounded up (80-lb bag 0.60 ft³, 60-lb bag 0.45 ft³, 25-kg bag 0.012 m³, 20-kg bag 0.010 m³). Weight = volume x 150 lb/ft³ (2,400 kg/m³). Stair angle = arctan(total rise / total run). Comfort check: 2 x riser + tread, near 24–25 in (61–64 cm).Example — the porch flight in the quick answer. Total rise 35 in, target riser 7 in, tread 11 in, width 4 ft, waist slab 6 in, waste 10%. Step one — risers: 35 / 7 = 5 risers, actual riser 35 / 5 = 7 in. Step two — treads: 5 - 1 = 4 treads. Step three — total run: 4 x 11 = 44 in (3 ft 8 in). Step four — slab length: √(44² + 35²) = √3,161 = 56.2 in (4.69 ft). Step five — slab volume: 4.69 ft x 4 ft x 0.5 ft = 9.37 ft³. Step six — wedges: ½ x 4 x 0.917 ft x 0.583 ft x 4 ft = 4.28 ft³. Step seven — total: 9.37 + 4.28 = 13.65 ft³ = 0.51 yd³ (0.39 m³); with 10% waste 15.01 ft³ = 0.56 yd³ (0.43 m³). Step eight — bags: 15.01 / 0.6 = 25.02, rounded up to 26 x 80-lb bags (34 x 60-lb, 36 x 25-kg, 43 x 20-kg). Net weight: 13.65 ft³ x 150 lb/ft³ = 2,047 lb (928 kg). Code check: riser 7 in (max 7.75) ✓, tread 11 in (min 10) ✓, width 48 in (min 36) ✓ — and 2 x 7 + 11 = 25 in, right in the comfort zone.

Worked example

The porch flight above, worked end to end: 35 in of total rise, 7 in risers, 11 in treads, 4 ft wide, 6 in waist slab — 5 risers, 4 treads, 44 in run, 13.65 ft³ (0.51 yd³) of concrete, 26 x 80-lb bags with 10% waste. The slab is the bigger half (9.37 ft³) and the wedges the smaller (4.28 ft³) — on a longer flight the slab dominates even more, which is why a steps-only estimate that forgets the slab runs short.

Porch steps by height (4 ft wide, 11 in treads, 7 in risers, 6 in waist slab, 10% waste — bag counts are 80-lb bags, rounded up):

StepsTotal riseRunConcrete (net)Order (with waste)80-lb bags
2 risers14 in (36 cm)11 in4.04 ft³ (0.15 yd³)4.44 ft³ (0.16 yd³)8
4 risers28 in (71 cm)33 in10.42 ft³ (0.39 yd³)11.46 ft³ (0.42 yd³)20
5 risers35 in (89 cm)44 in13.65 ft³ (0.51 yd³)15.01 ft³ (0.56 yd³)26
7 risers49 in (124 cm)66 in20.12 ft³ (0.75 yd³)22.13 ft³ (0.82 yd³)37
A two-step porch is a bag job (8 bags, one car trip); a seven-step flight is past half a yard and worth a ready-mix quote, especially once the short-load fee is compared against 37 bags at store prices.

Metric version: 0.9 m total rise, 18 cm target riser, 28 cm treads, 1.2 m wide, 15 cm waist slab, 10% waste. Risers: 90 / 18 = 5, actual riser 18 cm. Treads: 4. Run: 4 x 0.28 = 1.12 m. Slab length: √(1.12² + 0.9²) = 1.44 m. Slab: 1.44 x 1.2 x 0.15 = 0.26 m³. Wedges: ½ x 4 x 0.28 x 0.18 x 1.2 = 0.12 m³. Total: 0.38 m³; with waste 0.42 m³ — 35 x 25-kg bags (42 x 20-kg). Net weight: 0.38 m³ x 2,400 kg/m³ = 911 kg. Code check in metric: riser 18 cm against the 19.7 cm maximum, tread 28 cm against the 25.4 cm minimum — both pass.

Measurement tips

  • Model the slab and the wedges separately, and check both numbers. The slab length is a diagonal — longer than the run — so a slab priced on the horizontal run alone comes up short by the slope. The wedges are half-boxes: a steps estimate that prices every step as a full box doubles the wedge concrete.
  • Keep every riser identical, including the first and last. The bottom riser often needs trimming for the walkway thickness and the top riser for the porch flooring — forget either and one step is taller than the rest, which is exactly the trip hazard the 3/8 in code tolerance exists to prevent.
  • Form the steps from the bottom up, and brace for a blowout. Wet concrete pushes sideways on formwork with real force — a stair form that is only nailed, not braced and staked, spreads at the bottom step first. Brace every riser board to a stake, and check the width again after the first barrow goes in.
  • Pour the landing with the steps, not after them. A landing poured cold against cured steps leaves a joint at the busiest footfall on the flight. Form it as one pour with the stair, and the slab, wedges and landing cure as one piece.
  • Order ready-mix once the bag count passes about 45. A 5-riser porch at 26 bags is a comfortable bag job; a 7-riser flight at 37 bags is already a long afternoon of mixing, and past a yard the truck is usually cheaper per yard as well as faster.
  • Ask the plant about the short-load fee before you decide. Under about 3 cubic yards most plants add a fee that can exceed the concrete itself on a small pour — on a half-yard porch job, that fee is the difference between bags winning and the truck winning.
  • Cure the steps, do not just let them dry. Keep the concrete damp for at least 3–7 days (wet burlap or plastic sheeting) and keep foot traffic off for 48 hours. Concrete that dries out in the first day loses strength at the surface — the nosings, which take every footstep, are the first to dust and chip.
  • Put rebar or mesh in the waist slab, not just the wedges. A #4 bar each way in the slab (or 6x6 welded wire mesh) with 2 in of cover is the usual residential practice — the rebar calculator sizes the bars and the weight for the slab length this page prints.
  • Check the frost line before you dig the footing. Steps that sit on grade in a freeze climate heave and crack; the footing or base should sit below the local frost depth, and the post hole calculator carries the frost-line guidance for your state.
  • Finish the treads with a broom, not a trowel. A steel-troweled outdoor tread is slippery when wet; a light broom finish gives grip without looking rough, and it hides the small trowel marks a hand finish always leaves.

Common mistakes

  • Pricing each step as a solid box. The classic over-order: tread x riser x width x steps counts every step as a full rectangular block, but a step is a triangle — half a box. On the worked example that mistake orders 8.56 ft³ of wedges instead of 4.28 ft³, and the whole job comes out about 30% heavy.
  • Forgetting the waist slab entirely. The wedges alone are only a third of the concrete on a 5-riser porch — the inclined slab underneath is 9.37 ft³ of the 13.65 ft³ total. A wedges-only estimate runs short by two-thirds of a yard on a flight this size, which is a second trip or a cold joint.
  • Measuring the slab thickness vertically instead of perpendicular to the slope. A 6 in slab measured straight down is thinner than 6 in measured square to the slope — the difference is the cosine of the stair angle, about 12% at 38°. Measure square to the slope, as the formwork sees it.
  • Counting the top tread twice. The porch or upper floor is the final tread, so a 5-riser flight has 4 poured treads. Adding a fifth wedge prices concrete for a step that is already the porch — the same off-by-one that makes the run 11 in too long.
  • Planning risers at the 7.75 in code maximum. It is legal, but at 7.75 in risers with 10 in treads the stair is 38° and feels steep — most people find 7 to 7.5 in risers with 10.5 to 11 in treads much more comfortable, and the 2R + T check (24–25 in) says the same thing.
  • Pouring steps on uncompacted fill. Steps settle where the ground settles, and a stair that settles unevenly cracks at the waist and pulls away from the porch. Compact the base in lifts, and where the steps meet the house, tie into a footing that sits below frost depth.
  • Skipping the waste allowance on a small pour. Ten percent on a half-yard job is 0.05 yards — one extra bag or a short wheelbarrow. Running short mid-pour on a stair means a cold joint across the flight, which is worse than the dollar the saved bag was worth.
  • Ordering bags by the cubic yard without converting. A yard is 27 ft³ and an 80-lb bag yields 0.6 ft³, so a yard is 45 bags — not 27, not 40. The bag table on the concrete calculator lists every size; check your count against it before you pay.

Factors that affect accuracy

  • Total rise: the dominant factor — every riser adds a wedge and lengthens the slab diagonal. A 7-riser flight needs about five times the concrete of a 2-riser porch at the same width, not three and a half times, because the slab grows with the diagonal as well as the step count.
  • Stair width: volume scales directly with width. A 6 ft wide entry flight takes half as much concrete again as a 4 ft flight of the same rise — and it takes half as much again in formwork, bracing and finishing time too.
  • Waist slab thickness: the slab is the bigger half of the volume on most flights, so an inch of thickness is worth real concrete — going from 6 in to 8 in on the worked example adds about 3.1 ft³, roughly a fifth of the job. Thickness is a structural choice, not a place to save material.
  • Tread depth: deeper treads make wider wedges and a longer run, which lengthens the slab diagonal too. Going from 10 in to 12 in treads on a 5-riser flight adds about 0.7 ft³ of wedges and 0.4 ft³ of slab — a small price for a noticeably more comfortable stair.
  • Riser height: taller risers mean fewer steps for the same rise, so the wedge count falls — but the wedges get taller by the same proportion, and the slab diagonal barely changes. Riser height moves the step count and the comfort far more than it moves the volume.
  • Landing: a 3 ft landing at 4 in thick adds a flat 4 ft³ on a 4 ft wide stair — nearly a third of a 5-riser flight. Price it as its own line, as this tool does, or it quietly becomes the reason the pour runs short.
  • Waste allowance: 10% on steps versus 5% on flat slabs, because formwork leaks and the subgrade under a stair is uneven. On a half-yard job the difference is a single bag; on a two-yard flight it is four.
  • Subgrade and over-excavation: a stair dug into a slope rarely has a flat bearing surface, and every low spot in the excavation fills with concrete. Rough sites deserve 15% waste, not 10% — the same rule the concrete calculator applies to hand-dug ground.
  • Bags versus ready-mix: the crossover is about a cubic yard (45 x 80-lb bags). Below it, bags win on flexibility; above it, the truck wins on price per yard and on the crew's backs — 37 bags is over a ton and a half of lifting.
  • Ready-mix minimums and fees: short-load fees under about 3 cubic yards, and delivery distance, can add more than the concrete on a small pour. A half-yard porch job can cost more delivered than bagged once the fee lands — get the all-in number before choosing.

Sources & assumptions

  • Method — waist-slab stairs: the inclined slab plus triangular step wedges, per techraxy's concrete stairs calculator (steps = ⌈total rise ÷ max riser⌉, actual riser = total rise ÷ steps, run = (steps − 1) × tread, slab length = √(run² + rise²), slab volume = length × width × thickness, wedges = ½ × treads × tread × riser × width) and onlycalculators' concrete stairs calculator (wedge area = tread × riser / 2; carriage area = step hypotenuse × throat depth) and Concrete Calculator Max's staircase calculator (waist slab = thickness × width × √(run² + rise²); wedges = ½ × steps × tread × riser × width). This tool follows techraxy's step-count convention and the site's own stair calculator: treads = risers − 1, because the porch or upper floor is the final tread.
  • Code limits — 2021 International Residential Code §R311.7, confirmed 2026-11-11 against Plan7Architect's IRC stair calculator, RemodelCalculators' stair guide and PermitDeck's deck stair code: maximum riser 7¾ in (196 mm, R311.7.5.1), minimum tread 10 in (254 mm, nosing to nosing, R311.7.5.2), maximum ⅜ in variation between the tallest and shortest riser or tread in a flight, minimum stair width 36 in (R311.7.1), maximum 151 in of rise per flight (R311.7.3), nosing ¾–1¼ in where treads are under 11 in (R311.7.5.3). The 2 × riser + tread ≈ 24–25 in comfort rule is a rule of thumb, not code (Plan7Architect; MaterialGuides). The 2024 IRC renumbered the section to R318.7 without changing the dimensions.
  • Waist slab thickness — 5–7 in for residential spans per Concrete Calculator Max; 6–8 in throat depth per onlycalculators; 6 in is this tool's default. Thickness is measured perpendicular to the slope, not vertically.
  • Bag yields are the site's settled figures (QUIKRETE yields: 80-lb bag 0.60 ft³, 60-lb bag 0.45 ft³; 25-kg bag 0.012 m³, 20-kg bag 0.010 m³ — see the concrete calculator's sources). Fresh concrete weighs about 150 lb per cubic foot (4,050 lb per cubic yard), 2,400 kg/m³ per Concrete Calculator Max.
  • Why this page exists alongside the concrete calculator: that page's steps shape treats every step as a solid box (tread × riser × width) — its own limitations note says so — which prices the wedges at twice their true triangular volume. This page is the accurate waist-slab model; the slab page's steps shape remains only as a rough upper bound.
  • Canonical examples (this tool): rise 35 in, 7 in risers, 11 in treads, 4 ft wide, 6 in slab, 10% waste — 5 risers, 4 treads, 44 in run, slab length 56.22 in, slab 9.37 ft³, wedges 4.28 ft³, net 13.65 ft³ (0.506 yd³, 0.386 m³), order 15.01 ft³ (0.556 yd³, 0.425 m³), 26 × 80-lb bags (34 × 60-lb, 36 × 25-kg, 43 × 20-kg), net weight 2,047 lb (928 kg), angle 38.5°, comfort 25 in; code pass. Metric twin (0.9 m rise, 18 cm riser, 28 cm tread, 1.2 m wide, 15 cm slab): net 0.380 m³, order 0.418 m³, 35 × 25-kg bags. Landing case (defaults + 3 ft landing at 4 in): +4.00 ft³, net 17.65 ft³, 33 × 80-lb bags.

Figures checked on 28 November 2026 as part of the site-wide test run (3239 automated checks, all passing). See how we calculate and test.

Safety note

Wet concrete is caustic and can burn skin on prolonged contact: wear gloves, eye protection and boots, and wash any skin contact off promptly — never kneel in wet concrete. Stair formwork takes real sideways pressure: brace every riser board to stakes and re-check the width after the first barrow goes in, or the forms spread. Steps are heavy work — a 5-riser porch is over a ton of concrete — so get help lifting and placing it, keep the pour damp for 3–7 days while it cures, and keep foot traffic off for 48 hours.
Please note: material estimates are approximate. Always confirm product coverage with the manufacturer and buy a little extra for cuts, waste and future repairs.

What this calculator doesn't do

  • This tool models a waist-slab stair — an inclined slab with triangular step wedges on top, the way most poured porch and entry steps are built. A solid (mass) stair that fills the whole stepped profile down to the ground needs more concrete: its volume is tread x riser x width x n(n+1)/2, where n is the number of steps. If your steps are a solid stack or pre-cast units, this page is not the right model.
  • It sizes concrete volume, not the structure. Waist-slab thickness, rebar size and spacing, footing depth and whether the steps need their own footing below the frost line are structural and code questions — your plans or a structural engineer govern, and the local building department has the last word on permits.
  • The landing input is a simple rectangular pad the same width as the stair. A landing that ties into a porch slab, wraps a corner, or carries a roof post needs its own detail — price it as a slab on the concrete calculator if it is more than a plain pad.
  • Treads are counted as risers minus one, because the porch or upper floor is the final tread — the same convention as this site's stair calculator. If your top step is a poured tread rather than the porch surface, add one tread's wedge (half a box) to the volume, or count it as a one-tread landing.
  • Prices are optional inputs, not quotes. Ready-mix plants charge a short-load fee under about 3 cubic yards, and bagged mix is priced per bag at your store — enter your own figures. The cost line only appears when you enter a price.
  • The code check uses the International Residential Code (IRC) baseline for one- and two-family homes. Your jurisdiction may have adopted a different edition or local amendments — confirm the riser and tread limits with your building department before you form anything.

Concrete Steps Calculator — frequently asked questions

How much concrete do I need for concrete steps?

For a typical porch flight — 35 in of total rise, 7 in risers, 11 in treads, 4 ft wide, 6 in waist slab — you need 13.65 ft³ (0.51 cubic yards) of concrete, or 0.56 cubic yards with 10% waste. That is 26 x 80-lb bags, 34 x 60-lb bags, or 36 x 25-kg bags. Enter your own rise, width and slab thickness in the tool: the volume is the waist slab (9.37 ft³ here) plus one triangular wedge per tread (4.28 ft³ here).

How do I calculate concrete for steps?

Add two volumes. First the waist slab: slab length x width x thickness, where the slab length is the diagonal √(total run² + total rise²). Then the step wedges: ½ x number of treads x tread depth x riser height x width. A 5-riser porch (35 in rise, 11 in treads, 4 ft wide, 6 in slab) works out to 9.37 ft³ of slab plus 4.28 ft³ of wedges — 13.65 ft³ total, 0.51 cubic yards. Add 10% waste and divide by your bag yield (0.60 ft³ per 80-lb bag) for the bag count.

How many bags of concrete do I need for 5 steps?

For 5 risers at 7 in (35 in total rise), 11 in treads, 4 ft wide and a 6 in waist slab, you need 26 x 80-lb bags (or 34 x 60-lb bags) with 10% waste — the order volume is 15.01 ft³. In metric, the same flight is 0.42 m³, which is 36 x 25-kg bags or 43 x 20-kg bags. A 2-step porch needs only 8 x 80-lb bags; a 7-step flight needs 37.

What is the maximum riser height for concrete steps?

Under the International Residential Code (IRC R311.7.5.1), a riser may be no higher than 7 3/4 inches (19.7 cm) in a one- or two-family home, and no two risers in a flight may differ by more than 3/8 inch. The code minimum tread is 10 inches (R311.7.5.2). In practice, 7 to 7 1/2 inch risers with 10 1/2 to 11 inch treads climb far more comfortably than the code maximum — a stair at the limits is legal but steep, about 38°.

How thick should a concrete stair slab be?

The inclined waist slab is typically 6 inches thick for a low residential flight (5–7 inches is the usual residential range; some references allow 6–8 inches for the throat). Thickness is measured perpendicular to the slope, not vertically. For a flight that carries a roof, a landing load or a long span, the thickness is a structural decision — your engineer's figure governs, not a rule of thumb. This tool defaults to 6 inches.

Do concrete steps need rebar?

Yes — a waist slab without reinforcement cracks where the stair flexes and where it meets the porch. The usual residential practice is a #4 bar each way in the slab (or 6x6 welded wire mesh), with about 2 inches of concrete cover, plus dowels tying the flight into the porch or foundation. The rebar calculator sizes the bars and the weight from the slab length this page prints. Rebar does not change the concrete volume — it displaces a negligible amount.

Why does this give less concrete than the slab calculator's steps shape?

Because the two tools model different shapes. The concrete calculator's steps shape treats every step as a solid box (tread x riser x width) — a deliberately conservative shortcut, and its limitations note says so. This page models the real waist-slab profile: an inclined slab plus triangular wedges, each wedge half a box. On the worked example the box method prices 8.56 ft³ of wedges against the true 4.28 ft³ — about 30% more concrete for the whole job. Use this page for poured steps; use the slab page's steps shape only as a rough upper bound.

How much do concrete steps cost?

Materials only, the worked example (0.56 cubic yards ordered) is one short ready-mix load or 26 x 80-lb bags — enter your local per-yard and per-bag prices in the tool for both totals, and ask the plant about its short-load fee under about 3 yards, which can exceed the concrete on a small pour. Installed cost varies too much by region, access and formwork to quote here: get three local quotes against the same yardage this page prints, so every quote is pricing the same flight.

How many 25-kg bags of concrete do I need for steps?

A 25-kg bag yields 0.012 m³, so divide your order volume in cubic metres by 0.012 and round up. The metric worked example — 0.9 m rise, 18 cm risers, 28 cm treads, 1.2 m wide, 15 cm slab — needs 0.38 m³ net and 0.42 m³ with 10% waste, which is 35 x 25-kg bags (or 42 x 20-kg bags at 0.010 m³ each). A small 2-step porch in metric is about 0.11 m³, or 11 x 25-kg bags with waste.

What is the riser height for concrete steps in cm?

The IRC maximum is 19.7 cm (7 3/4 inches) and the minimum tread is 25.4 cm (10 inches), measured nosing to nosing. A comfortable metric flight uses about 18 cm risers with 28 cm treads — 2 x 18 + 28 = 64 cm, inside the 61–64 cm comfort band. Keep every riser identical within 1 cm in a flight; the code tolerance is 3/8 inch (9.5 mm) between the tallest and shortest riser.

Next step

Take the order volume, the bag count and the slab length to the supplier — and re-measure the formed width and slab thickness in the forms before you call, since a bowed form adds real volume. Then size the steel with the rebar calculator using the slab length this page prints, and check the footing depth against the frost line with the post hole calculator before you dig.

Save this estimate: use the Copy link button in the results box above to share these exact inputs, or Print results for a paper copy to take to the store.